Use Mermaid gantt to show work over time, dependencies, milestones, and project scheduling.

Gantt Chart

Use Mermaid gantt to show work over time, dependencies, milestones, and project scheduling.

Basic template

gantt
    title Sample Plan
    dateFormat  YYYY-MM-DD
    section Work
    Task A :a1, 2026-04-01, 3d

Core syntax

  • Start with gantt
  • Add title
  • Set dateFormat
  • Group tasks with section
  • Create tasks with:
    • Task :id, start, duration
    • Task :id, after otherId, duration
    • Milestone :milestone, id, date, 0d
  • Useful flags:
    • done
    • active
    • crit

Common example

gantt
    title Release Plan
    dateFormat  YYYY-MM-DD

    section Discovery
    Requirements      :done, req, 2026-04-01, 4d
    Design            :done, des, after req, 3d

    section Build
    Implementation    :active, impl, after des, 6d
    Testing           :test, after impl, 3d

    section Release
    Go Live           :milestone, go, 2026-04-18, 0d

Good for

  • Delivery plans
  • Migration windows
  • Project summaries

Watch for

  • Mermaid Gantt is strongest for lightweight planning, not full project management
  • Use real dates if the audience cares about calendar timing